Insulated!

April 16th, 2014 § 0 comments § permalink

One of the first modern commercial insulation products was made in Louisiana by Celotex of a material called bagasse, the pulp that remains after processing sugar cane.  Celotex produced their first insulation board in 1920 and it may have been what was used in the Temporary House when it built. The fellows who removed the lath and plaster from the old bedrooms found the dense matted material behind the lath and wedged into the spaces between the windows and the studs. It was very difficult to remove. A report written for the Midwestern Roofing Contractors Association in 1988 said that bagasse and wood pulp were the only remaining commercial products then available from the many different types that were tried through the 1920s and 1930s.

Below is a photo of the fibrous material we found in the house and the fluffy white stuff is very likely a material called rock wool, a precursor of fiberglass. The rock wool had once filled the stud cavities but ultimately had settled within the cavities—it wasn’t doing much insulating.

Bagasse insulation was made from sugarcane pulp. The white wispy stuff is an early form of fiberglass called rockglass.

Bagasse insulation was made from sugarcane pulp. The white wispy stuff is an early form of fiberglass called rockglass.

Nowadays, foam and fiberglass bats are the primary materials used for insulation. Foam is the better insulator, but is substantially more expensive. Straw, cellulose, and shredded denim are among some other less common, though recycled, insulating materials.

Once the rough electrical inspection was completed the insulating began. The first step was to use foam to seal all the cracks between the sheathing and studs. Roberto below used this orange foam that came in a can. After all of the cracks were sealed, the pink fiberglass bats went between the studs. Then plastic sheeting covered the studs, fiberglass, and window openings.

Filling all the gaps with foam.

Filling all the gaps with foam.

New kitchen space is insulated and plastic stapled in place

New kitchen space is insulated and plastic stapled in place

Upstairs the procedure was a little different since there are fewer cracks in the sheathing. Yet all of the possible sources of air leaks were hit with a shot of the orange foam. The pink fiberglass went between the studs except for the spaces where the ceiling angles down.There the space was too shallow for the fiberglass so it was filled with foam. That foam is beige. Reflective foil lines all of the areas that will be behind radiators. The upstairs will be very warm.

Foil is placed on top of the insulation in the areas where the radiators will be. The heat will be reflected back into the rooms.

Foil is placed on top of the insulation in the areas where the radiators will be. The heat will be reflected back into the rooms.

Another important aspect of the ceiling insulation is the use of plastic/foam panels to line the ceiling before the fiberglass bats are put in place. These panels have channels for the outside cold air to seep in and form a layer of cold air under the shingles. This way, ice and snow are less likely to melt on the roof and the melted water less likely to refreeze under the shingles and form ice dams.

Vent panels for the second floor ceiling create a cold air layer under the roof. This prevents ice dams.

Vent panels for the second floor ceiling create a cold air layer under the roof to prevent ice dams.

 

With the last of the “rough inspections” approved we are ready to coverup all of this fine “rough” work with drywall.

Inspectors Approval tags

Inspectors’  Approval tags

 

12 ft. long sheetrock panels being loaded into the house.

Drywall is next! One of sixty 12 ft. long sheetrock panels being loaded into the house.

 

 

 

Catching up

April 12th, 2014 § 0 comments § permalink

It has been almost three weeks since my last post. Some very major things were taken care of, but they were not so visually dramatic as those trusses going up. Below is most of what happened the first two weeks of the last three. Insulation will be in the next post.

First, the roof was shingled. You can see the roofers finishing up in the photo below.  If you look closely in the second photo you can see that portion of the roof ridge is higher in the middle than at the end. I thought the roofers hadn’t finished the ridge shingling. Rick told me that is the way it is supposed to be because of new roof venting requirements. I think I am the only house on the block with the new style of ridge vent. It does look unfinished though.The flat roof dormers got rubber roofing to replace the old metal roofs.

Roofing crew finishing up. See the rubber liner on the dormer.

Roofing crew finishing up. See the rubber liner on the dormer.

The roof vent does not completely cover the roof ridge. It is a new method of venting the roof.

The roof vent does not completely cover the roof ridge. It is a new method of venting the roof.

While the roofing was taking place the carpenters worked on various loose ends so that the new areas would be ready for the electricians. Code requires outlets every 3 feet along the kitchen counters and every six feet around the perimeter of each room. In addition each new closet will have a light—hooray! New smoke detectors in each bedroom throughout the house and in the hallways need to be connected on the same circuit. The downstairs hallway ceiling looks like swiss cheese. It took two electricians three days to complete the work. And this is just the rough electrical installation that precedes the sheetrock.

New ceiling electrical cans in any second floor room must have additional bracing to support a ceiling fan. I’m not installing ceiling fans, but someone may in the future, besides it is code. While I was photographing the ceiling fan supports I noticed some 2x4s in the ceiling area at unusual angles. Rick says that the Amish always add that kind of bracing to the  structure. It makes the house particularly stiff against high winds. The green cast to the upstairs pictures is from the green house wrap.

Bedroom ceiling light box. Note the extra bracing for a possible fan.

Bedroom ceiling light can. Note the extra bracing for a possible fan.

The kitchen area being wired. The papers pinned to the wall indicate where the outlet boxes, fixtures, and switched are to go.

The kitchen area being wired. The papers pinned to the wall indicate where the outlet boxes, fixtures, and switched are to go.

While the wiring was being installed, the pipes to the new radiators went in. We spent a lot of time trying to figure out exactly how to do it. The guys did a remarkable job of threading them through the walls and ceilings to the second floor, you can’t even tell that there was a concern.

OLYMPUS DIGITAL CAMERA

Heating pipe heading to the second floor.

Heating pipe heading to the second floor.

Next up, insulation.